A big box with a hard floor, blockwork walls and a metal deck roof. Sports halls are usually the worst-sounding rooms in a school, and the people who suffer most are the staff who have to make themselves heard in them all day.
The warning signs
- Instructions have to be shouted and still are not followed
- Staff finish the day hoarse
- Whistles and impacts are painfully loud
- Assemblies and exams in the hall are barely workable
Why the hall plays against you
The room is very large, so there is a great deal of air holding energy, and nearly every surface returns it.
Blockwork and metal deck absorb very little, so a shout keeps circulating for several seconds.
And because the hall has to take balls and equipment, the soft materials that would fix it cannot go just anywhere — which is exactly why sports halls get left alone.
The league table of fixes
BB93 sets the sports-hall limit by floor area (Table 7): 1.5 s under 280 m², rising on a sliding scale to 2.0 s above 530 m². Meeting BB93 is the normal way of satisfying Requirement E4 of the Building Regulations. Many existing halls measure well over three.
- 1about 300 m²Impact-resistant wall panels above ball height
The standard answer. Above roughly 2.5 m the panels are out of harm's way.
- 2about 380 m²Absorbent liner to the roof deck
Very effective, because the deck is the largest surface — but access decides it.
- 3about 260 m²Suspended ceiling rafts
Used where the roof cannot be lined; needs coordinating with lighting and nets.
- 4about 120 m²Retractable curtains, or divider nets with fabric
Partial, but it doubles as the court divider you may want anyway.
Indicative figures for the example room (33 × 18 × 7.5 m, about 4,455 m³), from the same method the report uses. Your room will differ, which is the point of checking it.
Post-match questions
Will panels survive being hit by a ball?+
Impact-resistant systems exist for exactly this and are what specifiers use. Standard fabric-faced panels will not last, which is why the usual approach is to treat above ball height.
Is this a BB93 compliance job?+
It can be, and if it is you will need a measured survey to confirm it. Our figure is indicative and meant for deciding what to do and roughly how much of it — a design guide, not a compliance measurement.
Our hall is also used for exams and assemblies. Does that change the target?+